POINTS TO SUPERVISE THE BRICK MASONRY WORK.
The following points should be kept in mind during supervision of brick work.
- Cleaning the entire floor, before starting the line out of masonry.
- Before using bricks, First check its physical properties like shape, dimensions and diagonal etc.
- Always laid the bricks having its frog facing upward.
- Tancha applied on column where vertical joint of masonry and RCC comes.
- The first course of brick should be perfectly in level.
- Confirm dimensions & diagonals of room after first layer (line out).
- First layer checked with beam top / bottom edge, offset & plumb.
- Opening to be provided at first layer for doors & at sill level for windows & A.C. units.
- Screening of sand,mortar proportion & soaking of bricks.
- Erection of door & window frames with necessary number of holdfast.
- Fixing of holdfasts to frames & to R.C.C. Columns if any.
- Racking of joints & surface cleaning after completion of day-to-day work.
- Thickness of joints not more than 12 mm.
- Cleaning of room
- Curing for 7 days.