As per IS 4130 - 1991

  1. Before start sabotage check all the electrical connections should be disconnected.
  2. If there any gas line in building then separate it with water line, steam line and any other services.
  3. If old building was deteriorate by any fire incident then support the roof or slab of building with props and C sections.
  4. Don't dismantling the building at night time if there any residence.
  5. Provide some supports to nearest building to prevent any harm of their walls.
  6. If there any feasibility of damage of nearest building then it is imperative to evacuate it.
  7. During the demolishing, workers should wear safety accessories like helmet, goggles, gumboot, hang gloves etc.
  8. At the area of dismantling, install a notice that this area is prohibited to enter.
  9. next to the site of sabotage, close the movement of men and vehicles.
  10. If the building is more than 7.5 meter height and traffic can't be stopped then install side walk shed of 4 meter height.